Contractor:
R&S Fire and Security Ltd
Architect:
Distributor:
VJ Technology Ltd
Location: Heathrow Airport Terminal 5
EJOT® Products
used: Low profile head, EJOT SAPHIR® JT2-FR-3 5.5 x 32
and JT2-FR-3 5.5 x 50 Bespoke solutions
Construction of the new Heathrow Airport
Terminal 5 (T5) started in September 2002; phase one of the
project is scheduled to be completed and open by April 2008
with the second phase following in 2011. The project is requiring
an estimated investment, mostly from the British Airports Authority
(BAA), of over £4.2
billion. Terminal 5 is a large infrastructure project involving
over 60 contractors, 16 major projects and 147 sub-projects
on a 260ha site.
EJOT® were one of several companies
approached by distributor VJ Technology Ltd, to offer a bespoke
solution to fix the nominated fire protection system."Primarily,
the customer needed a low profile carbon steel fastener for
fixing single (9mm) and double skin (18mm) Promat Durasteel
fire protection board to 3mm Metsec section" said
EJOT® Technical Sales Exec., Ben Gallant, "the project
was for the construction of passenger walkways, so their
brief placed high emphasis on aesthetics to complement the
engineered qualities".
VJ had already experimented with
a wide range of fasteners readily available on the market,
but couldn’t find an ‘off-the-shelf’ solution
that satisfied all criteria. "We provide specially manufactured
fasteners for particular details on a regular basis" explained
Ben, "so once again I looked to tap into this resource"
"We
started by trying several different types of low profile
head. The fasteners were based on our stainless steel bi-met
FR range and went from the drawing board of our design office
in Sherburn, to prototype in Germany, finally to onsite testing
at Heathrow. Final modifications were made and production/call
off of some 650,000 fasteners is being undertaken over a
10 month period." |